Hi :D

In usual gantt planners, it is possible to define dependencies between tasks.
Image

Thus, it is possible to define that :

    :arrow: task 1 will last for 20 days starting tomorrow,
    :arrow: task 2 will last for 4 days and won't start before task 1 is over,
    :arrow: etc.

Then the planner is able to process it and :

    :arrow: render all starting/ending task dates,
    :arrow: show what impact could have a delay in task 1 or 2 for instance.


I did not find out how to do this, is it even possible in OpenERP ?

_________________
Change for linux !
http://change-for-linux.tuxfamily.org


Top
 Profile  
 
 Post subject:
PostPosted: Wed Feb 10, 2010 11:38 am 
Offline

Joined: Tue Mar 04, 2008 11:41 am
Posts: 319
Location: Athens, Greece
There had been some patch (from chircar.at, I remember), long ago.

Some important work that needs to be done is to make sure the task planner algoritm works right (it is non-trivial). See this forum for previous discussions on the matter.

Perhaps we could make it in time and integrate this in 5.2.


Top
 Profile  
 
 Post subject:
PostPosted: Wed Feb 10, 2010 12:33 pm 
Offline

Joined: Wed Feb 10, 2010 10:26 am
Posts: 104
Hi,

though I'm totally unable to do this, I think it's possible to learn from opensource projets/software like Planner or Apache Ofbiz that already are able to perform such tasks.

PS : I didn't find the patch.

EDIT : where files should I check to see how difficult modifying the code could be ? I'm running Ubuntu 9.10

_________________
Change for linux !
http://change-for-linux.tuxfamily.org


Top
 Profile  
 
 Post subject:
PostPosted: Thu Feb 11, 2010 4:17 pm 
Offline

Joined: Wed Feb 10, 2010 10:26 am
Posts: 104
xrg wrote:
Perhaps we could make it in time and integrate this in 5.2.


Hi, after some other discussions it seems it is indeed scheduled for 5.2, by merging "Faces" project into OpenERP.

That would be great, I highly recommand it to be done :D

_________________
Change for linux !
http://change-for-linux.tuxfamily.org


Top
 Profile  
 
 Post subject:
PostPosted: Thu Aug 19, 2010 11:29 am 
Offline

Joined: Fri Apr 30, 2010 10:35 am
Posts: 90
so it will be included in v6, right?


Top
 Profile  
 
 Post subject: Re: Tasks dependencies
PostPosted: Thu Mar 03, 2011 9:18 am 
Offline

Joined: Sun Oct 03, 2010 8:33 am
Posts: 2
Hello there;
i need to know if tasks dependencies exist in openerp v6 or not????

please kindly reply


Top
 Profile  
 
 Post subject: Re: Tasks dependencies
PostPosted: Thu Mar 03, 2011 9:26 am 
Offline

Joined: Fri Apr 30, 2010 10:35 am
Posts: 90
perhaps you could have a look at phases, which offer previous/next phases and you could link you tasks to the phases?


Top
 Profile  
 
 Post subject: Re: Tasks dependencies
PostPosted: Fri Mar 04, 2011 9:07 am 
Offline

Joined: Tue Feb 02, 2010 4:43 pm
Posts: 8
Hello,

I was looking for task dependecies as well. In V6 you have phases (modules long term planning). Phases have dependecies and you can related tasks to every phase.
But as you can see from my own thread I was not able to successfully schedule a project.
Maybe someone can sched some light on this.


Top
 Profile  
 
 Post subject: Re: Tasks dependencies
PostPosted: Tue Apr 26, 2011 10:28 am 
Offline

Joined: Sat Jan 09, 2010 12:03 am
Posts: 32
Location: Romania
Hi folks!

I tested the Project Management module of the OErp, and the task dependence was not working.
I notified as bug (https://bugs.launchpad.net/openobject-addons/+bug/768889), and the team already made the modifications so the task dependence is OK now.
They were very fast!
Thank you!
Arpi


Top
 Profile  
 
 Post subject: Re: Tasks dependencies
PostPosted: Fri Feb 03, 2012 1:53 pm 
Offline

Joined: Mon Feb 15, 2010 5:52 pm
Posts: 22
Location: Paris
subscribing


Top
 Profile  
 
Display posts from previous:  Sort by  
Post new topic Reply to topic  [ 10 posts ] 

All times are UTC + 2 hours


You cannot post new topics in this forum
You cannot reply to topics in this forum
You cannot edit your posts in this forum
You cannot delete your posts in this forum

Search for:

Protected by Anti-Spam ACP