Hi, I have several parts in a finished product that require an external painting operation. -So we get in the unpainted part which I have defined as a product "BaseUnpainted" -We clean it up and check for defects then deliver it to the painting subcontractor which I have defined as a product "PaintingOperation" -After a few days the painting is done and we pick up the finished product "BasePainted"
I have defined the BOM for BasePainted including BaseUnpainted and PaintingOperation, the routing center is defined with the supplier location set. And auto picking is turned off.
When a sale is generated, this is what happens.
- MO generated for BasePainted in waiting goods state (good) - PO generated for BaseUnpainted and PaintingOperation (good) - When BaseUnpainted is received, delivery order to send BaseUnpainted to the subcontracter is generated (good) - when BaseUnpainted is delivered MO changes state to ready (good) - when I click consume and produce the finished product BasePainted is automatically moved from production -> stock (no good)
I want the finished product to move from production to the subcontractor location and have an incoming shipment or manual stock move to be generated for subcontractor -> stock
I can change the field "finished product location" manually but I would like the scheduler to handle this. Is this possible?
Thanks in advance.
Nick Schulze
|
|
| Top |
|
 |
|
Amgad
|
Post subject: Re: How To Change Finished Product Location in MO Posted: Thu Sep 15, 2011 5:47 pm |
|
Joined: Fri Sep 03, 2010 7:42 pm Posts: 11 Location: Cairo, Egypt
|
|
after checking the code, i think you can try the following: 1-in finished product configuration set the following: a- set the production location to the location of the subcontractor b- set the procurement location to the location where sales order should get product's from 2- in routing location set the location of raw material location
i hope this will be helpful.
regards, Amgad
|
|
| Top |
|
 |
|
NickSchulze
|
Post subject: Re: How To Change Finished Product Location in MO Posted: Fri Sep 16, 2011 1:06 pm |
|
Joined: Thu Sep 15, 2011 11:27 am Posts: 4 Location: United Kingdom
|
|
Thanks for the quick reply, Unfortunately it did not work. The production location in the MO changes to the supplier location, but the finished product location is still stock. If I can not figure it out I can just make sure that we only consume and product the MO when we receive the painted product. Cheers Nick Schulze
|
|
| Top |
|
 |
|
mihai
|
Post subject: Re: How To Change Finished Product Location in MO Posted: Fri Sep 16, 2011 1:25 pm |
|
Joined: Tue Jan 18, 2011 5:16 pm Posts: 236
|
|
Hi,
I am talking now without the program in front, but for product BasePainted you could create a new location that is internal location, and set that in the MO where you have Source And Destination location.
That could just work.
Mihai
_________________ OpenERP debugging with Eclipse on headless server
|
|